New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 91-100

EnsurepassQUESTION 91 You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost variance. What should you do?   View the Resource Graph’s Cumulative Cost view. View the Task Cost Overview report. View the Over Budget Tasks report. View the Cost Overrun report. Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 81-90

EnsurepassQUESTION 81 You are using Project Standard 2013. You want the ability to see only tasks that have finish dates past their deadline date. You need to achieve this goal using a custom field. What should you do?   Create a Lookup containing the values Yes and No against the Task Text1 custom field. Write a formula that compares the deadline date to the finish date and displays the correct value from the Lookup table. Use the Task Flagl5 custom field. Write a formula that compares Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 71-80

EnsurepassQUESTION 71 Drag Drop You are a project manager who uses Microsoft Project 2013. A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time. You need to bring on another resource to assist with the remaining 50% of the work Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 61-70

EnsurepassQUESTION 61 You are a project manager who uses Project Professional 2013. Your organization has been working with a new status report model for the last month. This new status report is created through the Built-in Dashboards and Reports in Project Professional 2013. The standard Project Professional 2013 report views named Late Tasks and Milestone Report already have all the information required for the new model. You are assigned to consolidate the information from these two reports into Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 51-60

EnsurepassQUESTION 51 You are a project manager who uses Project Professional 2013. You manage a project, which involves three other colleagues who also have experience in Project Professional 2013. You and your colleagues are over budget and cannot spend any more money in this project. You download a specific free app from the Microsoft Office Store. You need your colleagues to use the same app. What should you do?   Send the name or the link of the app to your colleagues. Then have them Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 41-50

EnsurepassQUESTION 41 You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create two manually scheduled tasks and link them in a Finish to Start relationship. The project team member asks you to increase the duration of the predecessor task. You notice that the successor task start date is now before the finish date of the predecessor task. You want the successor task to start after the predecessor Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 31-40

EnsurepassQUESTION 31 While creating a schedule with Project Professional 2013, you notice that there is a three-day duration on the Database Design task. After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished. You need to update the schedule with this information. What should you do?   Reschedule uncompleted work for the project schedule. Add two days of actual duration and change the remaining duration for the Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 21-30

EnsurepassQUESTION 21 You are a project manager for an organization that uses Project Standard 2013. You add shortcuts on the Quick Access Toolbar to your most frequently used commands. Your manager is impressed with the ease of use this customization provides and would like other project managers in the group to use it. You need to deploy the customization to these project managers. What should you do?   Save a Project File with the customizations to the ribbon in the file. Ask the other Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 11-20

EnsurepassQUESTION 11 You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours. What should you do?   Change the part-time resources’ Read more […]

New Updated Microsoft Specialist Certification 74-343 Real Exam Questions and Answers Download 1-10

EnsurepassQUESTION 1 You use Project Professional 2013 to manage a project that has customer-required milestone completion dates. You need to see graphically that your milestones have slipped beyond your customer-required dates. What should you add to the project milestones?   a Must finish on constraint a finish date a deadline a Finish no later than constraint   Correct Answer: C     QUESTION 2 You manage a project by using Project Professional 2013. Your project is updated Read more […]