QUESTION 21
You are a project manager for an organization that uses Project Standard 2013. You add shortcuts
on the Quick Access Toolbar to your most frequently used commands. Your manager is impressed
with the ease of use this customization provides and would like other project managers in the
group to use it. You need to deploy the customization to these project managers. What should
you do?
-
Save a Project File with the customizations to the ribbon in the file. Ask the other project
managers to open the file.
-
Email your global.mpt file to each project manager. Ask them to place the template in
the %appdata%MicrosoftMS Project15 1033 folder.
-
Click on the Import/Export button to export the customizations to a file. Ask the other
project managers to import the file.
-
Use regedit to export the following key: HKLMSoftwareMicrosoftOffice15.0User
SettingsProjectRibbon. Ask the other project managers to import the key.
Correct Answer: C
QUESTION 22
You are a project manager, and your organization uses Project Standard 2013. You have created a
non-working day in a resource’s calendar; however, the HR department notifies you that the
resource will work that day after all. You need to reflect this change in the project in the most
efficient manner. What should you do?
-
Open the Project calendar and mark the work day as working.
-
Open the resource’s working calendar and edit the Work Week details to set the day as
working.
-
Open the resource’s working calendar and delete the exception.
-
Open the resource’s working calendar and mark the day as working.
Correct Answer: C
QUESTION 23
You are a project manager who uses Project Professional 2013. All resources in your project
schedule have availability of 8 hours per day. You notice that several of the resources on the
project are overallocated. You decide to level the project to help resolve the overallocations for
the resources. Team members often do not work at the same time when completing their work
on the tasks. You need to resolve the overallocations by using the Resource Leveling function.
What should you do?
-
Click the Level only within available slack option.
-
Click Clear Leveling.
-
Click the Leveling can adjust individual assignments on a task option.
-
Click the Level resources with a proposed booking type option.
Correct Answer: C
QUESTION 24
You manage a project for an organization that relies heavily on schedule baselines in Project
Standard 2013. A change is approved for an in-progress project which you manage. You enter the
new tasks necessary to include the changes to the project schedule. You need to update the
baseline in the most efficient manner. What should you do?
-
Update the current baseline to the baseline1 fields.
-
Copy the current schedule to the baseline fields.
-
Select a range of tasks and update the schedule to the baseline1 fields for the selected tasks.
-
Select a range of tasks and update the baseline for the selected tasks.
Correct Answer: D
QUESTION 25
You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2. What should you do?
-
Enter physical percent complete for the tasks that have actual values. Set the Baseline to the
Baseline2, and reschedule uncompleted work based on the status date.
-
Change the Earned Value method to Baseline2 in the Task Information Form. Enter tracking
data, and view the VAC on the Earned Value table.
-
Change the Baseline for Earned Value calculation option to Baseline2, and reschedule
uncompleted work based on the status date.
-
Go to the Earned Value table and insert the Baseline2 column. Recalculate the project.
Correct Answer: C
QUESTION 26
You are a manager for an organization that uses Project Professional 2013. A critical project
shows average finish variance values between 5-10 days for the tasks. You need to interpret these
variance values to determine the next course of action to take. What do these variance values
mean?
-
The project is on schedule.
-
The project is running between 5-10 days ahead of schedule.
-
The project is running between 5-10 days behind schedule.
-
The project is averaging a normal performance timeline.
Correct Answer: C
QUESTION 27
You are a project manager who uses Project Professional 2013. When viewing the critical path,
you notice that there are some inconsistencies. To investigate the status of the critical path, you
insert the Total Slack column into a task table. You discover that many of the tasks have negative
Total Slack values. You need to resolve the negative Total Slack values. What should you do?
-
Remove lag time from task relationships.
-
Remove as many constraints as possible.
-
Re-assign resources that have more availability at the time of the negative slack.
-
Remove lead time from the task relationships.
Correct Answer: B
QUESTION 28
You manage a project by using Project Professional 2013. A critical task is out of scope for the
project. The stakeholders suggest that the task be removed from the project but kept in the plan
in case the task is needed in the future. You need to implement a solution to meet the
stakeholder’s request. What should you do?
-
Click on the task, and click Inactivate.
-
Move the task to after the ending date for the project.
-
Delete the task from the schedule.
-
Click the Unlink Task button to unlink the predecessors and successors for the task.
Correct Answer: A
QUESTION 29
You manage a project by using Project Professional 2013. The work variance for a task is 48 hours.
The remaining work is 25 hours. The work for this task has been completed. You need the work
variance to be adjusted to reflect what has occurred during the performance of the task. What
should you do?
-
Adjust the value in the Baseline Work column.
-
Enter a 0 in the remaining Duration column.
-
Adjust the value in the Work Variance column.
-
Mark the task inactive.
Correct Answer: B
QUESTION 30
You manage a project and use Project Professional 2013 to track your project schedule. One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at 50% of their availability. The resource asks to start the task three days later than planned because of a scheduling conflict. The schedule change is approved. You need to make the adjustment to the resource assignment to accommodate this request without affecting the other resources assigned to the task. What should you do?
-
Use the Resource Usage view and add duration to the assignment to extend the deadline
three days.
-
Use the Gantt Chart view tracking table and add a Start no earlier than constraint to the task.
-
Use the Task Form formatted to show Work Details and add a three-day delay to the
assignment for the resource.
-
Use the Task Form formatted to show Schedule Details and add a three-day delay to the
assignment for the resource.
Correct Answer: D
Instant Access to Download Latest Complete Collection of Microsoft Specialist Certification 74-343 Real Exam
Try Microsoft Specialist Certification 74-343 Free Demo
70-410 Dumps VCE PDF
70-411 Dumps VCE PDF
70-412 Dumps VCE PDF
70-413 Dumps VCE PDF
70-414 Dumps VCE PDF
70-417 Dumps VCE PDF
70-461 Dumps VCE PDF
70-462 Dumps VCE PDF
70-463 Dumps VCE PDF
70-464 Dumps VCE PDF
70-465 Dumps VCE PDF
70-480 Dumps VCE PDF
70-483 Dumps VCE PDF
70-486 Dumps VCE PDF
70-487 Dumps VCE PDF